How much are the permit, review and hook-up fees for a new cabin in Island Park, Idaho?
Corrected 18 November 2026: the county's site plan review fee now follows its fee schedule of 13 October 2026 (Resolution #2027-05).
The published 2026 figures run from $75 for the county's site plan review ($105 once the largest building passes 1,500 square feet) to a $7,458 hook-up fee where a county sewer system serves the lot, with Eastern Idaho Public Health's septic permit at $900 and the state's well drilling permit at $75 between them. The county building permit fee itself is not published anywhere this site could verify.
Government fees are the one part of an Island Park cabin budget that is published in advance — most of them. This page totals only what the county, the health district and the state actually print, and names plainly the fees no document prints. Everything here is from the county's Pre-Construction Check List for Building Permits (revised 17 April 2026), Eastern Idaho Public Health's fee schedule (effective 2 February 2026) and the Idaho Department of Water Resources.
The fees the documents print
| Fee | 2026 amount | Basis | Source and date |
|---|---|---|---|
| Site plan review | $75, or $105 once the largest building passes 1,500 sq ft | per review — a change after approval is charged again, at 65% of the original fee | Fremont County fee schedule, Resolution #2027-05, adopted 13 October 2026 (the Pre-Construction Check List, revised 17 April 2026, still prints the old $50) |
| Septic permit — new, expansion or repair | $900 | per permit | EIPH fee schedule, effective 2026-02-02 |
| Speculative site evaluation | $450 | pre-purchase evaluation; credited toward the permit if you apply within 1 year | EIPH fee schedule, effective 2026-02-02 |
| Septic permit transfer | $50 | per transfer | EIPH fee schedule, effective 2026-02-02 |
| Well drilling permit | $75 | single-family domestic well | Idaho Department of Water Resources (idwr.idaho.gov, retrieved August 2026) |
| Community-sewer hook-up | $7,458 | one-time, where a county sewer system serves the lot | Fremont County checklist, revised 17 April 2026; the county "lists the connection fee as $7,458 for both 2025 and 2026" |
The hook-up is the big one. The county's own wording: where community sewer is available in the Island Park/Mack's or Last Chance/Pond's system areas, "a hook up fee of $7,458.00 must be paid prior to receiving your building permit," and "These fees must be paid at the Fremont County Treasurer's Office after applying for the building permit." Budget it up front; it is one of the larger single fees in the whole process. Outside the sewered areas, the septic permit from Eastern Idaho Public Health — (208) 522-8065 — carries a $900 fee, and state rules "make it unlawful to build a system without one (Idaho administrative rule IDAPA 58.01.03)."
The site plan review has a trap worth pricing in: it "is charged again if you bring plans back for a change after approval, which is a small but real argument for getting the buildable envelope right before drawings are finalised rather than during." Under the county's October 2026 fee schedule, that second review costs 65% of the original fee.
The fees no document prints
Honest gaps, named as gaps:
- The county building permit fee itself — the plan-review and permit charge — is not printed on any page this site could verify. The instruction that travels with it: "Ask Planning & Building at (208) 624-4643 for the current figures when you file."
- Variance application fees — the code requires "the required application fee" but prints no amount; same desk, (208) 624-4643.
- City of Island Park application fees — the city code "sets no figures"; application fees are "as set from time to time by City Council resolution," so current numbers are a City Hall question.
- Driveway permit fees at county Road & Bridge, and Idaho Transportation Department approach-permit fees for US-20 frontage, are not published anywhere on this site.
What moves the number
- Sewer or septic. A sewered lot pays the $7,458 hook-up before its permit; an unsewered lot pays $900 to EIPH instead. Which fork you are on is a parcel question — confirm service to the specific lot.
- Plan changes. Every return trip after approval is charged another site plan review — 65% of the original fee under the October 2026 schedule.
- A hearing, if your project needs one. For Class II applications, Section 3.29.050 puts the actual cost of the mail and newspaper notices on top of the fee, "and then states the consequence plainly: no permit shall be issued until payment of all fees is received."
- Permit stacking — sometimes in your favor. Under Development Code section 3.02.040, "the Administrator may combine all required permits into one application and in his/her sole discretion only require payment of the fee of the highest cost permit." But "Multiple Class II permits will be publicly heard by the Commission individually and the Applicant shall be responsible for all public notice expenses of each."
How to get a real number
Call Planning & Building at (208) 624-4643 with the parcel number and ask for the building permit fee, the variance fee if one is in play, and any driveway-permit charge; call Eastern Idaho Public Health at (208) 522-8065 for the septic side. For the parts of the budget that are not government fees — well drilling, septic installation, driveway construction, power — the numbers are site-specific, and you can talk the lot through with us at (208) 656-1438.
FAQ
How much is the Fremont County building permit fee for a cabin?
Not printed. The county's own pages route the question to Planning & Building at (208) 624-4643 "for the current figures when you file." No number is invented here.
Is the site plan review the only review fee?
It is the printed one — but it "is charged again if you bring plans back for a change after approval," so a plan that has to return is more expensive than one that does not.
When do I pay the $7,458 sewer hook-up?
At the Fremont County Treasurer's Office, after applying for the building permit and before the permit is issued, per the county checklist revised 17 April 2026. The county listed the same figure for 2025 and 2026.
Do fees stack if my project needs several permits?
They may not: the Administrator may combine permits and "only require payment of the fee of the highest cost permit" (Development Code 3.02.040). Class II notices are the exception — each is heard and noticed individually at the applicant's expense.
Does the City of Island Park charge its own fees?
The city code sets no figures; fees come by City Council resolution, so the current numbers are a City Hall question — no fee figure appears on this page.
Is the septic permit part of the building permit fee?
No. It is a separate Eastern Idaho Public Health permit — $900 under the schedule effective 2 February 2026 — and the county wants it at building-permit submittal.