How do you file an Island Park cabin permit through Fremont County's new online portal?
What the portal takes, and what still travels on paper
"Fremont County is excited to announce that our new Planning & Building software system and public application portal are officially available!" (county newsflash, fremontcountyid.gov, retrieved 22 November 2026). It lists what the portal accepts:
Applications available through the new portal include: - Building Permits - Plats of All Types - Class I Permits - Class II Permits - Conditional Use Permits - Agricultural Structures - Zone Changes
Paper did not retire with it. The county's building permit application still reads: "Two sets of detailed plans and supporting documents (Engineering Calculations) and truss designs are required before approval of permit." And: "Plans must be submitted on a minimum of 11 X 17 paper." (Building Permit Application form, retrieved 22 November 2026.)
Filing through the portal, step by step
What goes into the application is on the guide to how to assemble a complete Fremont County building permit application; the filing channel itself runs in five steps.
- Match the application to the portal's list. A cabin's building permit is on it, with the Class I and Class II permits a larger project may need (county announcement, retrieved 22 November 2026).
- Have the two paper plan sets ready. Two sets of detailed plans, engineering calculations and truss designs, on paper at least 11 x 17, are required before approval of permit (Building Permit Application form, retrieved 22 November 2026).
- Sign, deposit, and pay the review fee. The land owner signs (Building Permit Application form). Fees follow the building: "Building permit fees are based on square footage and the type of construction (i.e. garage, residence, shed, carport). A DEPOSIT is due upon submittal." The form prints no deposit figure. The review fee is "$75, or $105 once the largest building passes 1,500 square feet" (county fee schedule of 13 October 2026).
- Wait out the review. "SUBMITTAL: The review process will require 7-10 working days." (Class I General Application form, retrieved 22 November 2026.) A lot on a county sewer system adds a second review: "The supervisor has up to 14 days to complete this review." (Fremont County Ordinance 2010-09, retrieved 22 November 2026.)
- Build inside the permit's life. "The permits are valid for TWO years, and the permit application must be signed by the land owner." (Building Permit Application form, retrieved 22 November 2026.)
| Number | As printed | Source |
|---|---|---|
| Plan review fee | $75, or $105 once the largest building passes 1,500 square feet | County fee schedule of 13 October 2026 (before-you-build page) |
| Review window | 7-10 working days | Class I General Application form, retrieved 22 November 2026 |
| Paper plan sets | Two sets, on a minimum of 11 X 17 paper | Building Permit Application form, retrieved 22 November 2026 |
| County sewer-system review | Up to 14 days | Fremont County Ordinance 2010-09, retrieved 22 November 2026 |
Where this goes wrong
- The form's fee line is out of date. The county's building-permit form still prints the older site-plan review figure that the October 2026 fee schedule replaced; the current fee is the schedule's $75, or $105 over 1,500 square feet.
- No deposit figure is published. It is calculated from square footage and construction type; ask for yours before you file.
- The paper logistics are not written down. The announcement does not say whether the two plan sets upload, mail or are handed in beside a portal filing, and it prints no account steps.
The close: ask the desk in writing
"Put the question in writing to Planning & Building, (208) 624-4643." Send first what no page answers: the deposit for your square footage, how the paper plan sets travel with a portal filing, whether the review fee is paid through the portal or at the desk, and whether an account is needed to begin. Read the complete-application guide for what must be in the application, and before you build for the steps around the permit. Call or text (208) 656-1438 with an Island Park build question.
Does the portal replace the county's paper building permit application?
No. Two sets of detailed plans, supporting documents and truss designs are still required before approval of permit, on paper no smaller than 11 X 17 (Building Permit Application form, retrieved 22 November 2026).
How much does it cost to file through the portal?
The plan review fee is $75, or $105 once the largest building passes 1,500 square feet (county fee schedule of 13 October 2026). A deposit is also due upon submittal, calculated from square footage and construction type, with no figure published (Building Permit Application form, retrieved 22 November 2026).
How long does Fremont County take to review a portal filing?
The Class I General Application form prints 7-10 working days (retrieved 22 November 2026). A lot on a county sewer system adds a review of up to 14 days (Ordinance 2010-09). Whether a portal filing reviews faster is not published in the sources this page uses.
Do I need an account to start an application?
The county's announcement names the portal but prints no account or login steps, so this page cannot say. Put the question in writing to Planning & Building at (208) 624-4643.
Who signs the application, and how long is the permit good?
The land owner signs, and the permit is valid for two years (Building Permit Application form, retrieved 22 November 2026).